No Gas-to-Energy Power for Christmas, Again: Jagdeo Moves the Deadline to March While GPL Tells Guyana to Brace for Blackouts

Bharrat Jagdeo says Guyana's Gas-to-Energy plant will not deliver power until March 2027, the latest in a string of missed deadlines. GPL meanwhile warns of periodic blackouts for generator maintenance.

No Gas-to-Energy Power for Christmas, Again: Jagdeo Moves the Deadline to March While GPL Tells Guyana to Brace for Blackouts
Illustration: AI-generated image

Guyana’s flagship power project has missed another deadline, and this time the government did not even wait for the date to pass before admitting it. Vice President Bharrat Jagdeo has confirmed that the first electricity from the Gas-to-Energy plant at Wales will not arrive this year. The new target for the simple cycle unit, about 220 megawatts, is the end of the first quarter of 2027, with the combined cycle to follow around June.

On the same weekend, Guyana Power and Light told customers on the Demerara-Berbice Interconnected System to expect “periodic” outages while it maintains its larger generators ahead of the Christmas peak. No schedule was published.

A Timeline Of Broken Dates

The record is damning. The contractor, Lindsayca, was originally expected to deliver the 300 MW plant and the natural gas liquids facility by the end of 2024. That date was missed. It slid to December 2025, then May 2026, then December 2026. Only recently, Public Utilities Minister Deodat Indar spoke of a commitment from the contractor to put 57 MW on the grid by December. Now even that has gone, and the vice president is offering March.

Jagdeo made the announcement at the Guyana Manufacturing and Services Association’s annual awards dinner, which is an apt setting. Manufacturers are among those paying most dearly for unreliable power and for the 50 per cent tariff cut that was promised on the back of this project and has not yet arrived.

The Cost Is Already Being Paid

While the plant sits unfinished, Guyana is renting two powerships from a Turkish firm. It was reportedly seeking a third, larger vessel that instead went to Venezuela, and the government has been trying to find an extra 20 MW to see the country through the holidays.

The financing is shifting too. The US Export-Import Bank approved a US$527 million loan for a project initially pegged at US$759 million. The final disbursement was due on 1 September 2026. The government asked to push it to 30 September 2027, and amendments tabled in the National Assembly show approval for a final disbursement on 30 December 2027. Lenders do not extend disbursement windows by more than a year for projects they expect to finish in March.

Who Should Answer

GPL says its maintenance cannot be deferred and that it will keep outages as short as possible. Perhaps so. But households and businesses are being asked to sit through blackouts in the middle of an El Niño season because the generation that was supposed to replace these ageing units is years late.

The government cannot keep announcing new dates without explaining why the old ones failed. What exactly has Lindsayca missed? What penalties has the state applied under the contract? How much has the delay cost in powership rentals and fuel? And why should anyone believe March when December, May and the December before that all came and went?

Guyana is one of the fastest-growing economies in the world and it still cannot keep the lights on reliably. That is not bad luck. It is a project management failure, and the people who own it should be named and made to account for it in Parliament.

0
0
Share this story

Leave a comment

Your email address will not be published. Required fields are marked *

More in Business

View all →

The Caribbean, delivered.

Business, community and culture from the islands and the diaspora, in your inbox.