Leguan Water Treatment Plant Opens: 701 Homes Get Clean Water, and Four More Plants Are Still on the Way
President Irfaan Ali has commissioned the Leguan water treatment plant, the first of five under Guyana's Water Supply Improvement Project. It serves about 701 households, but Success is still waiting to be connected.

The Leguan water treatment plant is the kind of project governments love to cut a ribbon on, and for once the ribbon is attached to something residents will actually feel: clean water coming out of the tap.
President Irfaan Ali commissioned the plant on Sunday on Leguan in Region Three. It is rated to produce two million litres of treated water a day for about 701 households, with lower iron content that should end the stained tiles and tanks islanders have lived with.
What We Know So Far
The facility is the first of five new water treatment plants under the government’s Water Supply Improvement Project to be commissioned and put into service. Ali said it fulfilled a commitment made to the people of Leguan and tied clean water to the dignity, health and quality of life of families.
He recalled families who once fetched water from underground sources early in the morning before children could go to school, and said the benefit should be obvious every time residents turn on their taps. A new transmission line is being installed to connect the Success community to the plant, with work expected to be done within the next month, after which, he said, every household on the island could get treated water.
The president also used the occasion to repeat that “Essequibo is Guyanese. And Essequibo shall remain Guyanese”, a reminder that in Guyanese politics no ribbon-cutting is ever only about the ribbon.
Good News With a Footnote
Credit where it is due. Clean water is not a luxury, and a working plant beats another feasibility study. Islanders who have scrubbed iron stains off their walls for years will judge this government by what comes out of the pipe, and on Sunday it delivered.
But the footnotes matter. This is one plant of five. The public deserves a clear timetable for the other four, where they are and when they will run. And the island is not yet fully served: Success is still waiting for its connection. A president who says the benefit should be evident whenever residents turn on a tap has set his own test. Some Leguan households cannot take it yet.
Water Is the Test of an Oil State
Guyana is now a country with money. That raises the bar. When public revenue is growing, there is less excuse for any village to drink iron-heavy water or to wait years for basic treatment. The real measure of the Water Supply Improvement Project will not be the first commissioning ceremony, but whether the last of the five plants opens on schedule and whether the water quality holds a year from now.
Leguan’s residents should hold the government to its words. If Success is not connected within the month, they should say so loudly. If the other four plants slip, the rest of the country should ask why. One plant is a promise kept. Five would be a policy.