Proman’s $270 Million Turnaround Hires 2,500 Workers for 34 Days. Point Lisas Should Ask What Happens on Day 35

Proman's TT$270 million plant overhaul at Point Lisas employs up to 2,700 people for 34 days. About 52 per cent of the spend stays local, which says a lot about the rest.

Proman’s $270 Million Turnaround Hires 2,500 Workers for 34 Days. Point Lisas Should Ask What Happens on Day 35
Photo: Kalamazadkhan / Wikimedia Commons (CC BY-SA 4.0)

For 34 days, Point Lisas is busy again. Proman is spending about TT$270 million on a planned shutdown and overhaul of its AUM downstream complex, with up to 2,700 people on site at the peak and more than 70 local companies engaged. It is welcome money in a slow economy. It is also a reminder of how thin the industrial estate’s employment story has become: the biggest hiring spree in the area is a maintenance job with an end date.

What the money buys

Work started on November 4, when the urea, urea ammonium nitrate (UAN) and utilities plants were shut for inspections, repairs and equipment upgrades. Production is due to restart on December 9, and the company says the work is on schedule. Turnaround manager Teresa Martinez told a media tour the job is critical to keeping the plants running safely and reliably until the next planned turnaround in 2029.

The headline tasks are not cosmetic. A nitric acid storage tank that had been working at only 44 per cent of capacity is being repaired; nitric acid is a key ingredient in UAN fertiliser. The stripper in the urea plant’s ACES loop is being inspected and maintained with overseas technical support, including from Toyo, which designed that process. A 26-tonne expander on the UAN plant is being replaced for the first time since the complex was commissioned in 2009. The company reports no major incidents or accidents so far.

Counting the local benefit

The figures are impressive on paper: more than 1,300 jobs across the three plants, about 1,800 people at the daytime peak and 2,500 to 2,700 including night shift, around 1.5 million man-hours across planning and execution. Proman expects about 52 per cent of the spending to stay in the local economy.

Read that last figure the other way and nearly half of the TT$270 million leaves the country, on imported parts, foreign specialists and overseas contractors. That is not a scandal; specialist plant work often needs specialist suppliers. But it is the honest measure of how much of Trinidad’s industrial base is still serviced from abroad, seventeen years after this complex opened.

The questions after December 9

A turnaround is good news for welders, riggers, scaffolders and caterers in the south for a month. It is not an industrial strategy. The Government and the energy chamber talk constantly about the downstream sector’s future; this is a chance to show what that means in practice. How many of the 2,500 are apprentices getting certifiable experience? How many local firms are doing work that used to go overseas, and how many will be able to bid for the next turnaround in 2029 without a foreign partner?

Proman deserves credit for maintaining its plants rather than running them into the ground, and for publishing its local-content estimate. The State should now do its part: track who got the work, publish what share of the skilled roles went to nationals, and use the next three years to raise the 52 per cent figure. Otherwise Point Lisas will keep enjoying a boom for five weeks every few years and wondering, in between, where the jobs went.

0
0
Share this story

Leave a comment

Your email address will not be published. Required fields are marked *

More in Business

View all →

The Caribbean, delivered.

Business, community and culture from the islands and the diaspora, in your inbox.