Seventeen Years, EC$200 Million, Two Missed Dates: St Jude Hospital Is Still Not Open

A year after St Jude Hospital was handed over, Saint Lucia's Government says full opening will slip to 2027. The Opposition calls it a con; both parties share the 17-year delay.

Seventeen Years, EC$200 Million, Two Missed Dates: St Jude Hospital Is Still Not Open
Illustration: AI-generated image

A year ago, Saint Lucia’s Government stood at St Jude Hospital in Vieux Fort and held a handover ceremony. Twelve months later the hospital is partly in use, the full opening has slipped into 2027, and the Opposition Leader is calling the whole thing “the greatest con in our nation’s history”. That is a politician’s phrase. The facts underneath it are bad enough without the adjective.

Where things stand

St Jude was destroyed by fire about seventeen years ago. Since then several administrations have had a hand in rebuilding it and none has delivered a fully working hospital. The physical structure was officially handed to the Ministry of Health in November 2025. The original plan was to open this year. The Government has since missed two projected opening dates.

Health Minister Moses Jn Baptiste, who is also the parliamentary representative for Vieux Fort North, where the hospital stands, confirmed on Monday that full transition is now projected for 2027. He says dialysis, administration, finance, kitchen, physiotherapy and laundry services are already operating on site, and that the move, “though not complete, is already benefiting hundreds of patients”. The delay, he explained, comes from a transition team of health professionals insisting on “rigorous testing”.

Opposition Leader Allen Chastanet wants a date. “After waiting for 17 years, today the people of the south are still waiting for a date that they can actually use the hospital,” he wrote. He pointed to EC$200 million in borrowing behind the reconstruction and demanded “a clear account of what was spent and what remains to be done”.

Nobody’s hands are clean

Chastanet argues his party warned against returning to the old site and that a purpose-built hospital already under construction would have been cheaper and quicker. Perhaps. But his own United Workers Party governed during part of those seventeen years, and that hospital was not opened on his watch either. The south has been failed by red and yellow alike, and voters there know it.

The Government’s position is no stronger. Rigorous testing is exactly what a hospital should have, and no minister should be pushed into opening wards that are not safe. But the time to discover how long commissioning takes was before the ribbon was cut, not after. Holding a ceremony for a building that would not treat an emergency patient for more than a year was a choice, and it was made for the cameras.

Meanwhile, at the stadium

The detail that should end the argument is in Chastanet’s statement: nurses have spent years caring for patients at a stadium. A generation of people in Vieux Fort and the south has been born, treated and in some cases has died in a sports ground converted into a hospital because successive governments could not finish a building.

“2027” is not a date. It is a year with twelve months in it. The minister should name the month in which the emergency department opens, publish what has been spent of the EC$200 million and what is left, and list what remains to be tested. If he cannot, then the people of the south are entitled to assume a third deadline is about to be missed.

0
0

More in Politics

View all →

Leave a comment

Your email address will not be published. Required fields are marked *

The Caribbean, delivered.

Business, community and culture from the islands and the diaspora, in your inbox.