EC$58 Million Spent, 15 Per Cent Built: The Arnos Vale Hospital Has ‘Slowed to a Halt’ and St Vincent Still Has No Finish Date or Final Price
Health Minister Daniel Cummings told Parliament the Arnos Vale hospital is about 15 per cent built after EC$58 million in spending, with no revised completion date. He blames the former ULP government; the fix is now his.

St Vincent and the Grenadines has spent about EC$58 million on a new national hospital that is roughly 15 per cent built, and the health minister cannot say when it will be finished or what it will finally cost. That is the state of the Arnos Vale hospital project as Daniel Cummings described it to Parliament on Tuesday.
Cummings called the arrangements “one of the most troubling for a project of that size”. He said work had “literally slowed to a halt” and promised that the government would “in short time” act to deal with problems involving both the contractor and the consultant.
The Numbers
The contract was signed in October 2024 and construction began that December, with completion originally scheduled for August 2027. Cummings put total spending at about EC$58 million, including supplies, against estimated work completed of EC$32.89 million, about 15 per cent of construction. The hospital is part of the Strengthening Health Resilience Project, financed by a US$125 million loan from Taiwan.
Asked by Opposition Senator Keisal Peters for the percentage completed, total spending, outstanding commitments and a revised commissioning date, the minister could offer no new date. A revised timeline and cost estimate, he said, will come only once the contractor and consultant issues are resolved.
The Blame Game
Cummings spent much of his answer on the previous Unity Labour Party government. He said the project has three components: the building and equipment; administrative and legal reforms with training; and project management. Under the second, he said, the former administration spent heavily on consultancies, including renting space in Kingstown for one adviser with secretarial support. He described that adviser as a former ULP candidate in South Leeward with no hospital management experience, and said nothing useful came from the assignment. He also said activity at the site increased before the 2025 election and dropped “significantly” afterwards.
Those are serious claims, and if they are accurate, Vincentians deserve to see the contracts, the payments and the outputs. A minister naming waste in Parliament should table the evidence, not just describe it.
Who Answers Now
But the New Democratic Party has been in office since November 2025. A year on, the problem is no longer only its predecessor’s. The money spent so far is a debt that Vincentians will repay on the Taiwan loan whether or not the hospital opens. Every month of drift adds to the bill and delays care.
Cummings also confirmed the government’s position that Arnos Vale will be the country’s main hospital, with no further hospital at the Milton Cato Memorial Hospital in Kingstown. That raises the stakes further. If the new facility is the future of national healthcare, its management cannot be left to vague promises of action “in short time”.
The minister should return to Parliament quickly with three things: what exactly has gone wrong with the contractor and consultant, what contractual remedies the state is using, and a realistic completion date with a costed plan. Until then, Arnos Vale is less a hospital than a very expensive building site.