US$130 Million for Norman Manley Airport While Passengers Fall 1.4%: Daryl Vaz Is Paving the Runway for Flights That Keep Leaving
Daryl Vaz says US$130 million is going into runway, apron, customs and solar projects at Norman Manley, as passenger traffic slips 1.4 per cent and flights to Florida thin out.

Kingston is spending big on an airport that fewer people are using. Energy, Transport and Telecommunications Minister Daryl Vaz says roughly US$130 million is going into four major projects at Norman Manley International Airport, and in the same speech he admitted passenger traffic between January and September was about 1.4 per cent below last year.
That is not an argument against the money. It is an argument about priorities, and about who answers if the concrete arrives before the airlines do.
Where the Money Goes
The biggest item is US$62 million for runway and safety-area improvements, due in November 2027. Replacing apron slabs will cost US$52 million, due in December 2027. A new customs and transit hall costs US$7 million and should be ready by July 2027, and the second phase of the airport’s solar farm, worth US$9 million, is due for handover in December 2026. Another US$10 million is set aside for supervision and engineering.
Vaz, speaking at an airport forum in Kingston on November 24, told the private operator PAC Kingston Airport Limited to deliver on time, on budget and to standard. Its chief executive Héctor Cortés pointed to a renewed aerodrome certificate, two industry accreditations and more than US$125 million in works under contract.
The Number That Matters
The minister was candid about the weak spot. Spirit Airlines’ departure hit Fort Lauderdale traffic hard, and Miami departures fell from 148 to 139. Load factors rose from about 76 per cent to almost 82 per cent, which Vaz summed up as fewer flights carrying more passengers.
Read that the other way round and it is a warning. Fuller planes on fewer flights mean less choice and, usually, higher fares for the Kingston traveller, the diaspora visitor and the business that ships people in and out of the capital. A runway built to last decades does nothing for a family paying more to fly to Florida for Christmas.
Vaz says the priority must be to protect existing routes and attract more capacity. Good. But the government did not announce a single new carrier, route or incentive alongside the US$130 million. Copa and British Airways adding frequencies is welcome; it is not a strategy.
Who Should Be Held to Account
Safety work on a runway is not optional, and nobody should begrudge it. The customs hall matters too; Vaz is right that a visitor’s first impression of Jamaica should be efficiency, not a queue. The solar farm is sensible.
The accountability question is simpler. The operator has the contracts and the deadlines. The ministry has the job of making sure Kingston does not keep losing flights while Montego Bay and now even Boscobel win them. The minister also flagged the November 13 US aviation ground stop that disrupted both main airports, and said Jamaica must be ready to manage such shocks. That means contingency plans the public can see, not just promises made at a hotel forum.
US$130 million buys a better airport. Only airlines buy a busier one. Vaz should be measured on the second.