2,500 Jobs for 34 Days: Proman’s Shutdown Shows How Thin Point Lisas’ Lifeline Has Become
Proman's US$40 million maintenance shutdown at Point Lisas is giving 2,500 people work for 34 days. Next year's shutdowns depend on new gas contracts with NGC.

Two and a half thousand people have work at Point Lisas this month. By 9 December most of them will not. That is the uncomfortable truth underneath the cheerful numbers coming out of Proman’s maintenance shutdown, and it says more about the state of Trinidad and Tobago’s energy economy than any ministerial speech.
The turnaround in numbers
Proman is spending US$40 million, about TT$270 million, on a 34-day turnaround at its AUM downstream complex, which makes nitrogen-based fertiliser. The company says the exercise will provide temporary employment for 2,500 people, with more than 70 local contractors engaged and roughly 1.5 million man-hours across planning and execution. Turnaround Manager Teressa Martinez put the share of spending expected to stay in the local economy at about 52 per cent.
Work began on 4 November and production is due to resume on 9 December. Head of Corporate Communications Colin Greaves said the job was on schedule, with no major safety incidents by day 14 and more than 1,800 workers on site at peak daytime hours. Among the repairs is a nitric acid storage tank that had been running at just 44 per cent of capacity, a constraint on fertiliser output.
The good, plainly stated
This is real money reaching real people. Welders, scaffolders, fitters, caterers and maxi drivers are earning this month because a private company chose to hire locally. More than half the budget staying in the country is a respectable figure, and two weeks without a serious accident on a site that size is not luck. Proman should be thanked for both.
The sentence that matters
Then read what Deputy Managing Director Giselle Thompson said about next year. The company plans two turnarounds, but “all based on being able to negotiate new gas contracts with the NGC, because in order to do the turnarounds, we need to have some certainty around gas supply for the future years”.
There it is. The jobs, the contracts and the spending all hang on whether the National Gas Company can promise gas, and at what price. No certainty, no maintenance. No maintenance, and plants that already run below capacity run lower still, until somebody decides they are not worth keeping open.
Point Lisas was built on cheap, plentiful gas. The gas is no longer plentiful, and every downstream operator is now negotiating from the same anxious position. Meanwhile the skilled tradesmen who keep the estate alive live from shutdown to shutdown, 34 days at a time, with nothing in between. That is not an industrial workforce. It is a casual labour pool with very expensive qualifications.
What the Government owes these workers
Ministers enjoy touring plants during turnarounds. The harder job is at the negotiating table. The Government, through NGC, should tell the country where gas supply talks with downstream companies stand, what volumes it can actually commit and for how long. Workers deserve to know whether there will be two turnarounds next year or none.
A month of full car parks at Point Lisas is welcome. It is also a reminder of how quiet the estate could become if the gas question keeps being answered with hope.